The house
gets a real driveway. |
|
Summer 2005 pictures of the house. |
|
The house gets a new fountain
in front. |
|
Week 49
Mowed the grass for the first time, sealed driveway and garage concrete
and shelving in the garage. |
|
Week
47
Grass planted and straw spread.
|
|
House
Warming Party
We take time to celebrate with friends and family.
|
|
Week
43
Landscaping and exterior finishing starts.
|
|
Week
42
Some finishing touches and concrete.
|
|
Week 38
Shower and Mirrors installed and starting to feel moved in.
|
|
Week 36
Moving, final grading, gutters, and a lot of little stuff.
|
|
Week 35
Septic, final interior paint and trim, garage doors and openers,
carpeting, and final electric line.
|
|
Week 34
Stairs continue, master bath tile set, hardwood floors sanded, stained
and sealed, electrical installed, garage floor poured, and most supply
plumbing finished. |
|
Week 33
More stair work, general trim work, sump pump installed, and water
supply lines started. |
|
Week 32
Cabinets installed, hardwood floor laid, stairs started, and water
installed. |
|
Week 31
Trim installation, doors installed stained and lacquered, cabinets
arrive, and well drilled. |
|
Week 30
Windows stained, interior doors, trim arrives and is stained, brick
almost completed. |
|
Week 29
First coat of interior paint, kitchen tile laid, and hardwood floor
arrives. |
|
Week 28
Exterior doors, front porch finished, and tile started. |
|
Week 27
Drywall taped and sanded, doors delivered, and heat runs for five days. |
|
Week 26
Front bricks started, front siding and window finished, and drywall
started. |
|
Week 25
Insulation finished and drywall delivered. |
|
Week 24
Electrical and plumbing rough-in finished and pre drywall inspections. |
|
Week 23
Basement windows, deck, fireplaces, humidifiers, water supply lines,
more siding, and more electrical. |
|
Week 22
Front and back porches poured, electrical started, furnaces, gas, and
more siding. |
|
Week
21 Siding started, more soffets and fascia, and central vacuum
installed. |
|
Week 20 Soffets
started and windows finished. |
|
Week 19
Windows, rough stairs, 3500 feet of -ethernet, cable, speaker
wire, more HVAC , and more plumbing. |
|
Week 18
Shingles complete, plumbing rough-in, and more HVAC. |
|
Week
17
Complete roof rafters and sheathing, HVAC starts, and the snow finally
melts. |
|
Week
16
Top roof ridge installed with a flag! |
|
Week 15
Porch roofs are complete. Several other roofs started. Electric service
installed -and more snow. |
|
Week
14
Second floor walls finished, roof started, and more snow in the master
bedroom! |
|
Week
13
Back porch, garage, some second floor walls, and 3" of snow in the
master bedroom! |
|
Week
12
Garage and second floor walls and an ice storm. |
|
Week
11
First floor walls inside and out in -16° weather, snow! |
|
Week
10
First floor -floor, basement floor poured, and a few walls! |
|
Week
9
Knee walls, electrical service and engineered floor beams!
|
|
Week
8
Basement walls after backfilling and media room floor poured.
|
|
Week
7
Basement walls poured
|
|
Week
6
Foundation pouring
|
|
Week
5
Finish foundation forms
|
|
Week
4
Start setting foundation forms
|
|
Week
3
Pouring footings and the stuck cement truck |
|
Week 2
Setting footing forms
|
|
Week 1
Digging the hole
|
|
Before
Digging |
|